The Trust Company Australia (Limited) ATF WH Regent Trust will deliver a new 18 storey building and use for student accommodation and retail purposes at 90-102 Regent St in Redfern.

Key Features

  • 408 beds across 18 storeys

  • Demolition of existing above ground structures and limited excavation to Expand and lower the existing basement level

  • Construction of an 18 storey (plus basement and rooftop plant) building comprising podium (2 levels) and tower (16 levels) elements

  • Public art integration to façade at various location to enhance the Community Streetscape

  • Building Setback and activation of William Lane

  • Small retail unit at ground floor on Regent Street

  • remainder of the building to be used for student accommodation, including

    • 381 single and double occupancy rooms

    • Student communal facilities including lounge areas, quiet and study areas, communal kitchens and dining areas, gym, games area, cinema, communal outdoor spaces, and parking for 134 bicycles

Overview

Above ground demolition work expected to commence in September/October 2021. Main construction work expected to commence in October/November 2021 with an expected completion May 2023. As the project progresses, updates will be published to this website and relevant stakeholders notified.

Planning Instrument

SSD 10382_Construction Certificate 2

SSD-10382-Mod-1 Stamped Plans

SSD 10382 MOD 1 - Assessment

SSD 10382 MOD 1 - Instrument

SSD 10382 MOD 1 - Consolidated Consent

SSD10382 Construction Certificate 1

SSD 10382 Instrument of Determination

SSD 10382 Assessment Report

SSD 10382 Approved Plans

SSD 10382 Notice Of Decision

Management Plans & Reports

Green Travel Plan

Operational Plan of Management

SSD 10382 Construction Compliance Report - #7 January 2024

SSD 10382 Construction Compliance Report - #6 October 2023

SSD 10382 Construction Compliance Report - #4 April 2023

SSD 10382 Construction Compliance Report - #3 December 2022

Tower Crane Dismantle

Notification of works - 13/06/2023

Notification of works - 24/05/2023

Water main upgrade

Sewer connection

Williams lane occupancy 13/05/22

Commencement of construction

Williams lane occupancy 14/02/22

Williams lane occupancy 09/02/22

Williams Lane occupancy 25/11/21

Demolition

Tower Crane Erection

Notifications

Newsletters

90 - 102 Regent St Newsletter 08/02/2024

90-102 Regent St Newsletter 22/06/2023

90 - 102 Regent St Project Update 18/03/2023

90 - 102 Regent st Newsletter 18/03/22

90 - 102 Regent St Newsletter 18/03/2023

Complaint Register

Month 24 January 2024

Month 23 December 2023

Month 22 November 2023

Month 21 October 2023

Month 20 September 2023

Month 19 August 2023

Month 18 July 2023

Month 17 June 2023

Month 16 May 2023

Month 15 April 2023

Month 14 March 2023

Month 13 February 2023

Contact & Inquiries

If you have any questions or concerns, please contact the team on:

​

​

The community email and phone number will be managed during the following hours:

​

  • Monday – Friday: 8.30am – 5.30pm

Registration of Interest

Quarterly updates will be sent to our subscribers list and also posted below as construction progresses. You can subscribe to receive these updates by entering your email address below.

Thanks for submitting!

bottom of page